Inst ToolsInst ToolsInst Tools
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
  • Request
Search
  • Books
  • Software
  • Projects
  • Process
  • Tools
  • Basics
  • Formula
  • Power Plant
  • Root Cause Analysis
  • Electrical Basics
  • Animation
  • Standards
  • 4-20 mA Course
  • Siemens PLC Course
Reading: SIS Maintenance – Safety Instrumented System
Share
Font ResizerAa
Inst ToolsInst Tools
Font ResizerAa
  • Courses
  • Design
  • PLC
  • Interview
  • Control System
Search
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
  • Request
Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Inst Tools > Blog > Safety Instrumented System (SIS) > SIS Maintenance – Safety Instrumented System

SIS Maintenance – Safety Instrumented System

It is very important to perform timely maintenance on Safety Instrumented System (SIS) for the safe, reliable operation of the plants.

Last updated: April 27, 2022 4:18 pm
Editorial Staff
Safety Instrumented System (SIS)
No Comments
Share
6 Min Read
SHARE

It is very important to perform timely maintenance on Safety Instrumented System (SIS) for the safe, reliable operation of the plants.

Contents
Brief of SIS MaintenanceRules for SIS MaintenanceResponsibilitiesMaintenance – Proof Testing RequirementsDocumenting Proof TestLogic Solver Testing

SIS maintenance is also auditable by external certifying agencies on Safety systems (applicable as per the government regulations, varies in each country).

Brief of SIS Maintenance

As plant facilities having SIS goes into operation, Maintenance has three primary responsibilities:

  • Perform SIS-related proof-testing.
    • Define the frequency of SIS components to be proof-tested. 
    • Perform SIS repairs as needed.
      • This is to ensure the time up to which a sensor in multiple configurations can be allowed to stay out of service. Normally this shouldn’t exceed twice the scheduled frequency, otherwise, higher-level management authorization is required.
    • Always maintain documentation about the results of SIS test and repairs
      • The results of all tests and services performed on the SIS should be documented.  This should note whether the service was planned or unplanned (including plant trip).
Safety PLC System
Image Courtesy: Yokogawa

Rules for SIS Maintenance

SIS proof test intervals shall be established based upon Safety Integrity Level (SIL) and SIS configuration (hardware and software).

Proof test intervals are to be calculated using relevant tools for SIS and ensure it meets the safety requirement. 

Periodic proof test documentation shall be kept for at least the last 2 tests to ensure the SIS integrity, if tests aren’t confirming the SIS requirement additional testing is to be planned.

Responsibilities

The responsibility of the plant maintenance team is to do proper maintenance of SIS in order to ensure that the required SIL of each safety instrumented function is maintained and to confirm the designed functional safety is maintained for the plant.

Maintenance – Proof Testing Requirements

The SIS shall be designed in accordance with the maintenance and testing requirements. A proof test is a physical test to determine if there are problems with an SIS or BPCS IPL component that the online diagnostics does not check.

For example, for a sensor, this could be plugging in the sensor line, a pinhole in the diaphragm, or undetected electronic drift.  The proof test brings out faults/problems on the instrument if any. 

Depending on redundancy and application, the proof test may require instruments to be pulled out of service or process units to be shut down. This is why it is very important to consider proof testing when designing an SIS.

In all cases, the goal of proof testing is to return the component to “as good as new”, so that the healthiness of the instrument is ensured.

Documenting Proof Test

The plant shall maintain records that certify that proof tests and inspections were completed as required.

These records shall include the following information as a minimum:

  • Type, details of tests and inspections performed
  • The date on which the tests and inspections have taken up
  • Maintenance person name who performed the tests and inspections
  • Instrument/Valves serial number or other unique identifier, e.g. loop number, tag number, equipment number, and SIF number
  • The results of the tests and inspection and values, e.g. “as-found” and “as-left” conditions

SIS Valves Leak Test Requirements

The performance of all SIS components must be periodically proven via proof testing including SIS category valves.

The degree to which an SIS valve is leak tested is determined by its required functionality.  Based on the plant/ unit criticality some valves may require zero leakage.

Those valves that are determined to require a “bubble tight” leak performance (also called tight shutoff) due to exceptionally low leak limits necessary to maintain risk mitigation need to demonstrate this level of performance. Options for bubble-tight testing are conducting bench testing in a valve shop or in-line testing.

In some cases, SIFs can accept large leak rates as per calculations while maintaining risk mitigation. The leak test for the final element in this application/ service may be a visual inspection and checking in the field for stem movement by an experienced instrument technician.

Logic Solver Testing

Proof testing, Repair, and Documentation procedures also apply to the logic solver.

The maintenance frequency of the logic solver may be different than the sensor & final control elements, usually the Proof testing of the logic solver is matched with the plant’s Turn Around or Major overhaul frequency so that the operations are not affected.

Even though the plant goes for shutdown the logic solver functionality may need to be retained to maintain some essential services viz. cooling water, Steam, etc.

The logic solver hardware must be periodically tested according to a written proof test procedure to detect unsafe/undiagnosed failures.

Don't Miss Our Updates
Be the first to get exclusive content straight to your email.
We promise not to spam you. You can unsubscribe at any time.
Invalid email address
You've successfully subscribed !

Continue Reading

Reliability of a Control System
Safety Integrity Level (SIL)
SIS Design – Safety Instrumented System
Importance of Safety Integrity Level
ESD System Insights: Signals for Emergency Valve Shutdown Explained
Layers of Protection Analysis (LOPA) Interview Questions
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Copy Link
Share
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

128.3kFollowersLike
69.1kFollowersFollow
210kSubscribersSubscribe
38kFollowersFollow

Categories

Explore More

Difference between Process shutdown and Emergency Shutdown
SIS Verification & Validation – Safety Instrumented System
What is Emergency Shutdown System (ESD) ?
S84 / IEC 61511 Standard for Safety Instrumented Systems
What is HIPPS System in Oil and Gas?
Rupture disks
Bathtub Curve
Safety Instrumented System Probability

Keep Learning

Logic Solver in Safety PLC

What is a Logic Solver? – Safety PLC

Functional Safety Exam Questions & Answers

Functional Safety Questions & Answers

Safety Instrumented System Engineer Interview Questions

Safety Instrumented Systems Online Exam

Purpose of Emergency Shutdown (ESD) System

Purpose of Emergency Shutdown (ESD) System

Basic Terms used in SIL Verification

Basic Terms used in SIL Verification

Emergency Shutdown System Philosophy

Shutdown Philosophy

Emergency Block Valve

SIS Emergency Block Valves (EBV)

Difference between SIS, PLC and BPCS Systems

Difference between SIS, PLC and BPCS Systems

Learn More

D’Arsonval Movement

D’Arsonval Movement

Studio 5000 Logix Emulate Controller

How to Create New Project in Studio 5000?

PLC control 4 machines with 1 button

CX-Programmer Tutorial: 1 Button To Activate 4 Different Machines

Auto Changeover Switch

What is an Auto Changeover Switch?

PID Controller Functionality

PID Controller Loop Tuning Tips

Air Circuit Breaker (ACB)

Types of Relays used in an Air Circuit Breaker (ACB)

Self-balancing Pneumatic Instrument Principles - 3

Self-balancing Pneumatic Instrument Principles

level gauge

Basics of Sight Glass Level Gauge

Menu

  • About
  • Privacy Policy
  • Copyright

Quick Links

  • Learn PLC
  • Helping Hand
  • Part Time Job

YouTube Subscribe

Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?