This is a PLC Program for the selective execution of the application.
Problem Description
There are pigments of three colors. We need to fill different pigments into the jar by selecting the selector switches.
Implement the PLC program using a ladder programming language.
In this system, we will consider S7-300 PLC and TIA portal software for programming.
Here we need to fill different pigments in the jar as per requirement. So consider 3 types of different color pigments (Yellow, blue, and green.).
Two valves are used for controlling the pigments. (As we know mixing of yellow and blue is green color so there is no need of separate valve for green color.)
When both yellow and blue color are filled at the same time, it will become green color. Selector switch is used for color selection in the system and ON/OFF switch is used for system STOP.
When ON/OFF switch (I2.0) is ON and START PB is pressed, Cycle ON (Q0.0) lamp will be ON.
If cycle is ON and yellow color pigment is selected (I0.2), yellow color control valve (Q0.1) will be ON.
If cycle is ON and blue color pigment is selected (I0.3), blue color control valve (Q0.2) will be ON. If green color pigment is selected (I0.4), both the valves will be ON and pigment will become green color.
If you liked this article, then please subscribe to our YouTube Channel for PLC and SCADA video tutorials.
You can also follow us on Facebook and Twitter to receive daily updates.
Read Next:
Omron PLC logic for sorting the number of products and counting the number of products…
Learn the water fountain control logic using the PLC timers programming to control the high…
Open Telemetry is a framework for collecting data in cloud-native applications including tracing, metrics, and…
This article is about controlling the Pneumatic cylinder and Pneumatic motor in the assembly line…
In this post, we will learn the basic requirements for a network switch to be…
The PLC panel and MCC panel interface signals are start, stop, run feedback, trip, local…