Inst ToolsInst ToolsInst Tools
  • Courses
  • Videos
  • Q & A
    • Interview
      • Instrumentation
      • Electronics
      • Electrical
      • Practical Questions
    • MCQ
      • Instrumentation MCQ
      • Electrical MCQ
      • Electronics MCQ
      • Control Systems MCQ
      • Analog Electronics MCQ
      • Digital Electronics MCQ
      • Power Electronics MCQ
      • Microprocessor MCQ
      • Multiple Choice Questions
  • EE
    • Electronics
      • Electronics Q & A
      • Electronic Basics
      • Electronic Devices & Circuits
      • Electronics Animation
      • Digital Electronics
    • Electrical
      • Electrical Basics
      • Electrical Q & A
      • Power Electronics
      • Electrical Machines
      • Electrical Animation
      • Power Systems
      • Switchgear & Protection
      • Transmission & Distribution
  • Measure
    • Control Valves
    • Calibration
    • Temperature
    • Pressure
    • Flow
    • Level
    • Analyzers
    • Switches
    • Vibration
    • Solenoid Valve
  • Control
    • PLC Tutorials
    • Control Systems
    • Safety Instrumented System (SIS)
    • Communication
    • Fire & Gas System
  • More
    • Design
    • Tools
    • Animation
    • Basics
    • Formulas
    • Standards
    • TextBooks
    • Common
    • Software
    • Excel Tools
    • Erection & Commissioning
    • Process Fundamentals
    • Videos
    • Books
Search
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Reading: Wrong Operation Internals Destroyed Demineralization Mixed Bed Vessel
Share
Notification Show More
Font ResizerAa
Inst ToolsInst Tools
Font ResizerAa
  • Courses
  • PLC Tutorials
  • Control Systems
Search
  • Courses
  • Videos
  • Q & A
    • Interview
    • MCQ
  • EE
    • Electronics
    • Electrical
  • Measure
    • Control Valves
    • Calibration
    • Temperature
    • Pressure
    • Flow
    • Level
    • Analyzers
    • Switches
    • Vibration
    • Solenoid Valve
  • Control
    • PLC Tutorials
    • Control Systems
    • Safety Instrumented System (SIS)
    • Communication
    • Fire & Gas System
  • More
    • Design
    • Tools
    • Animation
    • Basics
    • Formulas
    • Standards
    • TextBooks
    • Common
    • Software
    • Excel Tools
    • Erection & Commissioning
    • Process Fundamentals
    • Videos
    • Books
Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Inst Tools > Blog > Root Cause Analysis (RCA) > Wrong Operation Internals Destroyed Demineralization Mixed Bed Vessel

Wrong Operation Internals Destroyed Demineralization Mixed Bed Vessel

Root Cause Analysis (RCA): Ruined Demineralization (Demin) vessel internals threaten indefinite Ammonia plant shutdown.

Last updated: September 28, 2022 3:15 pm
S Raghava Chari
Root Cause Analysis (RCA)
No Comments
Share
4 Min Read
SHARE

Root Cause Analysis (RCA): Ruined Demineralization (Demin) vessel internals threaten indefinite Ammonia plant shutdown.

Contents
Demineralization Mixed Bed Vessel ProblemConstraintsAuthors Improvisation
Article Type:Root Cause Analysis (RCA)
Category:Mechanical
Equipment Type:Pipelines and Miscellaneous Problems
Author:S. Raghava Chari

Note: This root cause analysis (RCA) is from real-time scenarios that happened in industries during the tenure of two or three decades ago. These articles will help you to improve your troubleshooting skills and knowledge.

Demineralization Mixed Bed Vessel Problem

Wrong operation internals destroyed demineralization (De-min) mixed bed vessel need readying within 8 hours because of the following:

  1. De-min tank level will last max 9 hours only
  2. Demin water production not resumed within 8 hours will shut down the 1500 T/d NH3 plant
  3. Not meeting the hard won international orders involves heavy financial & image loss
  4. NH3 plant shutdown (SD) and restarts are time & efforts intensive, thermally stresses the plant equipment and shortens their lives

Constraints

  1. No spare parts available
  2. Rush Air freight from Japan takes minimum 2 months

Authors Improvisation

below described is the Authors Improvisation:

  1. Scouted the local market and made a vendor deliver in an hour the readily available 2” CPVC pipes; pipe-caps, 10 Nos. hand held drilling machines, 50 Nos. ½ mm drill bits and PVC glue 2 cans
  2. Shop crew cut 80 mm long rings out of the damaged laterals’ usable portions
  3. They machined the ring bores to to slide fit on 2” CPVC pipes. They glued the rings to the pipes cut to lateral lengths and the caps at the other end
  4. All – mechanics, electricians, and instrument mechanics – drilled numerous ½ mm dia holes all over the CPVC pipe guided by a wrapped round ½ mm brass strainer sheet.
  5. Homemade two in one lateral and distributor assembly (LDA) making progressed
  6. Field crew went on inserting the readied LDA in the demin vessel central vertical pipe sockets. Thus the demin vessel was ready for resin charge in 5 hours!
  7. Operation crew charged the resin and mechanical crew boxed the vessel. The demin vessel was ready in 7 hours, though the allowed time was 9‑hours!

With a vigorous prayer, operators started de-mineralization. As good quality as before demin water surprised all. The doom predicted ‘exerts’ grudgingly congratulated the author.

Author improvisation benefits:

Below listed the Author improvisation benefits:

  1. Demin water production resumption in 7 hours averted the 3 months or even longer ammonia plant shutdown, missed export deliveries’, penalties, and the debuting company’s image loss etc.
  2. Laterals and distributors several hundred dollars purchase saved
  3. A ready solution to handle future mishaps if any was in hand

The author made LDAs were still in service when he retired 5 years later.

Author: S. Raghava Chari

Do you face any similar issues? Share with us through the below comments section.

If you liked this article, then please subscribe to our YouTube Channel for Instrumentation, Electrical, PLC, and SCADA video tutorials.

You can also follow us on Facebook and Twitter to receive daily updates.

Read Next:

  • Gas Cooler Re-tubing
  • Rotary Granulator Drive
  • Problems with Demister Pads
  • Steam Letdown Station Problems
  • Bucket elevators Chain Problems
Don't Miss Our Updates
Be the first to get exclusive content straight to your email.
We promise not to spam you. You can unsubscribe at any time.
Invalid email address
You've successfully subscribed !

Continue Reading

Compressor Anti-Surge Control near-miss incident
Instrumentation Engineering Problems Solved – Root Cause Analysis
Readers Questions on Flow Transmitter
Plant Shutdown Analysis: Valve Closed and SOV Coil Failure
Poorly Engineered, built & often Failing Plant Air Compressor Drives
Poor Electrical Heating Element Lives – Problem Solved
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Copy Link
Share
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

128.3kFollowersLike
69.1kFollowersFollow
208kSubscribersSubscribe
38kFollowersFollow

Categories

Explore More

Frequent Feeder-A Lightning Arrester (LA) Bursts – Root Cause Analysis
Pressure Correction Pneumatic Instrumentation
Unstable & Drifting Values of Differential Pressure Transmitter Problem
Seawater Pipeline Spools from day-1 leaks threaten Plant Shutdown
Steam Turbine Driven Centrifugal Compressors Leak due to Broken Instrument
Less than 40% available Plant Air Compressors made available 100% for Operations
Under and Over-Capacity Control Valve Pose Poor Controllability
Seal Level Differential Pressure Transmitter Problems
Carbamate Plunger Pump Packing Problems Eliminated
Problems with Demister Pads – Root Cause Analysis (RCA)

Keep Learning

Steam Pressure Taps Primary Block Valves Glands and Bonnets Leaks

Instrument Steam Pressure Taps Primary Block Valves Glands and Bonnets Leaks

Capacitor Bank

Poor Power Factor Boosted – Industrial Electrical Problems

CO2 Stripper Old Differential Pressure Transmitter Stopped Working

CO2 Stripper Old Differential Pressure Transmitter Stopped Working

Boiler Feed Water Heater Shell Flange Leaks

Boiler Feed Water Heater Shell Flange Leaks

Control Panel Instruments

Control Panel Instruments Problem Threatened Plant Shutdown

11 kV, 3.3 kV, and 400 V systems insulation resistance (IR) Problems

11 kV, 3.3 kV, and 400 V systems insulation resistance (IR) Problems

Control Valve Whisper Trim Cage

Problem with Choked Control Valve with Whisper Trim Cage

Erratic Radar Level Gauges

Erratic Radar Level Gauges Delays a Refinery Commissioning

Discover More

Derivative Controller Response

Derivative Controller Principle

Serial Communication Data Transmission Modes

Serial Communication Data Transmission Modes

Power Systems Questions & Answers

Power Systems MCQ Series 15

Thermostatic valves Principle

Thermostatic Valves Working Principle

Lube Oil Console

Immersion Heaters in Lube Oil Consoles

Counter Count Down Bit

Down Counter PLC Program

Measurement of Voltage Objective Questions

Measurement of Voltage Objective Questions

Difference Between Solenoid Valve and Motorized Valve

Difference Between Solenoid Valve and Motorized Valve

Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?