Inst ToolsInst ToolsInst Tools
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
Search
  • Books
  • Software
  • Projects
  • Process
  • Tools
  • Basics
  • Formula
  • Power Plant
  • Root Cause Analysis
  • Electrical Basics
  • Animation
  • Standards
  • 4-20 mA Course
  • Siemens PLC Course
Reading: PLC Timer Programming Examples – TON, TOF, TP and TONR
Share
Notification Show More
Font ResizerAa
Inst ToolsInst Tools
Font ResizerAa
  • Courses
  • PLC
  • Control Systems
Search
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Inst Tools > Blog > PLC Tutorials > PLC Timer Programming Examples – TON, TOF, TP and TONR

PLC Timer Programming Examples – TON, TOF, TP and TONR

Discuss about PLC Timer Programming Examples - Different PLC Timers are TON, TOF, TP, and TONR. PLC Timer Instructions and Timer logics.

Last updated: November 1, 2023 2:49 pm
Editorial Staff
PLC Tutorials
2 Comments
Share
7 Min Read
SHARE

Discuss about PLC Timer Programming Examples: Different PLC Timers are TON, TOF, TP, and TONR. PLC Timer Instructions and PLC Timer logic examples.

Contents
PLC Timer ProgrammingProblem DiagramProblem SolutionList of Inputs/OutputsPLC Ladder diagram for TimersRuntime Test Cases

PLC Timer Programming

Implementation of IEC timers (TON, TOF, TP &TONR) in S7-1200 PLC using TIA Portal.

In many applications, there is a requirement to control time or signal flow. For example, a valve, or a motor might need to be controlled to operate for a particular interval of time, switched ON after some time interval or after some delay.

Problem Diagram

PLC Timer Programming
PLC IEC Timers

Problem Solution

For this problem, we will use IEC timers (TON, TOF, TP &TONR) in S7-1200 PLC with examples.

There are a number of different forms of timers that can be found in PLCs. As shown in the above diagram,

  • ON delay timer which becomes ON after a particular time delay.
  • Off delay timers are ON for a fixed period of time after turning OFF input.
  • Pulse timer switches ON or OFF for a fixed period of time.
  • Accumulator timer is which records time intervals.

Here consider the example of four motors and four SWITCHES for an explanation of timers. We need to start three motors in different ways.

  1. The first motor will start after a 10 sec delay,
  2. the second motor will start immediately and off after a 10 sec delay and
  3. the third motor will start with a pulse and off with a 10-second delay.
  4. The fourth motor will run for a total of 10 sec.

List of Inputs/Outputs

Inputs List

  • SWITCH 1: I0.0
  • SWITCH 2: I0.1
  • SWITCH 3: I0.2
  • SWITCH 4: I0.3
  • Reset: I0.4

Outputs List

  • MOTOR 1: Q0.0
  • MOTOR 2: Q0.1
  • MOTOR 3: Q0.2
  • MOTOR 4: Q0.3

PLC Ladder diagram for Timers

We can use the Generate-ON-delay or ON delay timer instruction to delay the setting of the Q output by the programmed duration PT. The instruction is started when the result of the input IN changes from 0 to 1 (positive edge).

You can monitor the current time value at the ET output of the Timer block. The timer value starts at T#0s and ends when the value of duration PT is reached. The ET output is reset as soon as the signal state at the IN input changes to 0.

PLC ON Delay Timer

We can use the Generate off-delay or off-delay timer instruction to delay resetting of the Q output by the programmed duration PT.

The Q output is set when the result of the logic operation (RLO) at input IN changes from 0 to 1 (positive signal edge).

We can monitor the current time value at the ET output.

PLC OFF Delay Timer

We can use the Generate pulse instruction to set the output Q for a programmed duration.

The instruction is started when the result of the input IN changes from 0 to 1 (positive edge).

Programmed time (PT) begins when the instruction starts. In this timer even if a new positive edge is detected, the signal state at the output Q is not affected as long as the PT time duration is running.

PLC Pulse Timer

The Time accumulator instruction or accumulator timer is used to accumulate time values within a period set by the programmed time (PT) parameter.

When the signal state at input IN changes from 0 to 1 (positive edge), the instruction is executed, and the duration PT starts.

In this case, the Q parameter remains set to 1, even when the signal state at the IN parameter changes from 1 to 0″(negative edge). The R input resets the output Q.

PLC Accumulator Timer

Program Description

In this problem we will consider S7-1200 PLC and TIA portal software for programming.

Network 1:

In this network we have used ON delay timer (generate on delay) for MOTOR 1(Q0.0).

When the status of the SWITCH 1(I0.0) changes from 0 to 1 the timer instruction will be executed and it will activate the MOTOR 1(Q0.0) after 10s delay.

Network 2:

In this network we have used off delay timer (generate off delay) for MOTOR 2(Q0.1).

When the status of the SWITCH 2(I0.1) changes from 0 to 1 the timer instruction will be executed and it will activate the MOTOR 2(Q0.1) immediately.

Also when the SWITCH 2(I0.1) status changes back to 0 then programmed time (PT) will start and after time MOTOR 2(Q0.1) will be OFF.

Network 3:

In this network we have used pulse timer (generate pulse) for MOTOR 3(Q0.2).

When the status of the SWITCH 3(I0.2) changes from 0 to 1 the timer instruction will be executed and it will activate the MOTOR 3(Q0.2) immediately.

In this case even new positive edge is detected, the status of the MOTOR 3(Q0.2) is not affected as long as programmed time (PT) is running.

Network 4:

In this network we have used accumulator timer (accumulator time) for MOTOR 4(Q0.3).When the status of the SWITCH 4(I0.3) changes from 0 to 1 the timer instruction will be executed and MOTOR 4(Q0.3) will start after 10s.

The MOTOR 4(Q0.2) will remain ON, even when the input status changes back to 0.The Reset (I0.4) is necessary to reset the timer or accumulated time.

Runtime Test Cases

PLC Timers Example

Author: Bhavesh

If you liked this article, then please subscribe to our YouTube Channel for PLC and SCADA video tutorials.

You can also follow us on Facebook and Twitter to receive daily updates.

Read Next:

  • Alarm and Trip Systems
  • Allen Bradley PLC Programming
  • PLC Input and Output Modules
  • Analog Input Conversion Formula
  • Car Parking PLC Progam
Don't Miss Our Updates
Be the first to get exclusive content straight to your email.
We promise not to spam you. You can unsubscribe at any time.
Invalid email address
You've successfully subscribed !

Continue Reading

PLC Program for Trash Compactor
PLC Program for Control Valve Scaling
VFD Pros and Cons – Variable Frequency Drives
Peripheral Inputs and Outputs in Siemens PLC
How to Configure Analog Inputs and Outputs in Delta PLC?
Why is RTO used in the Place of TON Timer?
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Copy Link
Share
2 Comments
  • Kumar says:
    March 23, 2024 at 2:59 pm

    Thank you very much dear sir for your efforts

    Reply
  • Ray says:
    July 14, 2024 at 2:47 am

    Thank you sir.

    Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

128.3kFollowersLike
69.1kFollowersFollow
208kSubscribersSubscribe
38kFollowersFollow

Categories

Explore More

Motor Feedback Fail Logic in PLC
ON and OFF a Group of Outputs by One Push button PLC Logic
Establish Communication Between Two PLC Via PROFIBUS Protocol
What is an RTU? – Remote Terminal Unit
Best 100 PLC Projects for Final Year Engineering Students
Steps to Configure TCP/IP Communication in Siemens S7-1200 PLC
How to Use an SQL Server with Indusoft Web Studio?
Glass Cutting and Polishing Machine: PLC Automation Solution

Keep Learning

PLC Programming for Level Switches

PLC Programming using Level Switches

Configuration of Siemens VFD Using TIA Portal

Configuration of Siemens VFD Using TIA Portal Start drive

Design Counters in PLC Programming With a Move Instruction

Design Counters in PLC Programming With a Move Instruction

Ladder Logic Programming Examples

Ladder Logic Programming Examples

Grounding or Earthing Scheme in DCS or PLC Systems

Grounding or Earthing Scheme in DCS or PLC Systems

Latched and Momentary Operation of Motor PLC Program

Latched and Momentary Operation of Motor PLC Program

Advanced Skills Required for a PLC Programmer to Get a Job

Advanced Skills Required for a PLC Programmer to Get a Job

Factory Acceptance Test of PLC Panel

Factory Acceptance Test (FAT) of a PLC Panel

Learn More

Micro 870 Rockwell PLC

Rockwell Automation Allen Bradley PLC for Smaller and Medium Projects

Why Calibration is Important

Why Calibration is Important?

Power Electronics Objective Questions

Three-Phase Rectifier Quiz

What Every Instrument Engineer Should Know

What Every Instrument Engineer Should Know?

Forward reverse motor control diagram with timer

Timer during Motor Direction Change PLC Program

Siemens S7 300 CPU Status and LED Errors Explanation

Siemens S7 300 CPU Status and LED Errors Explanation

Diode Rectifier

Bridge Rectifier Working Animation

Types of Interrupts Organization Blocks in Tia Portal

Types of Interrupt OB in Siemens Tia Portal

Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?