Inst ToolsInst ToolsInst Tools
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
  • Request
Search
  • Books
  • Software
  • Projects
  • Process
  • Tools
  • Basics
  • Formula
  • Power Plant
  • Root Cause Analysis
  • Electrical Basics
  • Animation
  • Standards
  • 4-20 mA Course
  • Siemens PLC Course
Reading: P&ID Guidelines for Centrifugal Compressor Systems
Share
Font ResizerAa
Inst ToolsInst Tools
Font ResizerAa
  • Courses
  • Design
  • PLC
  • Interview
  • Control System
Search
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
  • Request
Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Inst Tools > Blog > Erection & Commissioning > P&ID Guidelines for Centrifugal Compressor Systems

P&ID Guidelines for Centrifugal Compressor Systems

Last updated: June 20, 2019 9:48 am
Editorial Staff
Erection & Commissioning
No Comments
Share
6 Min Read
SHARE

Typical P&ID for a centrifugal compressor system

P&ID Guidelines for Centrifugal Compressor Systems

    1. Proper centrifugal compressor symbol should be selected first, as shown in figure-1. Normally, a centrifugal compressor is accompanied by a Knock Out Drum (KOD) at the compressor suction and an aftercooler at the compressor discharge, as per a typical compressor PFD. Symbols for these equipments should also be placed on the P&ID before proceeding ahead. All the equipment symbols should be selected from the legend sheets of a particular project.
    2. All the nozzles on the compressor, suction drums and aftercooler should then be correctly represented with size and flanges. This includes inlet and outlet nozzles and equipment drains / vents as shown in the typical P&ID in figure-1.
    3. Centrifugal compressor suction KOD is intended for removing the entrained liquids before sending gas to the compressor. Demister, mesh pad etc. are used in the knock out drum to efficiently remove the liquid droplets.
    4. Compressor aftercoolers are generally air coolers and the related fan, motor etc. should be clearly indicated on the P&ID. If cooling water is used, proper symbol for a heat exchanger should be used.
    5. Inlet, outlet lines for each equipment, anti-surge line, drain/vent lines, line to the relief valve etc. are the next to be drawn up. Line number, material class, size etc. is to be correctly assigned to each of the lines.
    6. Isolation valves, spectacle blinds, spacers etc. to be used for maintenance should be drawn up next on various lines between the equipments. Requirement for isolation valves, spectacle blind, spaces etc. depend on the project standards, which should be followed while indicating these on the P&ID. Sometimes, to minimize the number of isolation valves between the equipment, they can be placed only at the suction KOD inlet which is inlet of the centrifugal compressor system and discharge of the aftercooler which turns out to be the outlet of the centrifugal compressor system. Spectacle blinds or spacers can be used for isolation between individual equipments for quick maintenance. This is simply a guideline and project standards need to be followed when indicating the isolation requirements.
    7. A check valve should be normally provided on the compressor discharge to avoid reverse flow when the pump is not in operation.
    8. Pressure relief valves can be provided on the compressor discharge line, downstream to the check valve, to protect the equipments downstream of compressor.
    9. Pressure gauges should be provided on suction and discharge of the compressor. Level gauges need to be located on the compressor suction knock out drum and temperature gauges on inlet, outlet lines for the aftercooler.
    10. Pressure transmitters should be provided on compressor suction and discharge line. A flow transmitter should be provided on compressor suction line. Signals from these transmitters are sent to an ‘Anti-Surge Controller’. Based on the gas flow and differential pressure head developed by the compressor, the anti-surge controller operates the anti-surge valves to prevent compressor surge condition.
    11. An anti-surge line from the aftercooler discharge to the suction KOD inlet should be provided for anti-surge control. When the compressor approaches surge condition (low flow, high differential head), the anti-surge valves open up to lower the pressure differential and circulate higher gas flow.
    12. Sometimes, a performance controller can be included in the centrifugal compressor system to control the rotating speed (RPM) of the compressor based on inlet pressure, flow etc. in order to achieve optimum performance. Performance controller will typically adjust the motor/turbine speed.
    13. Level transmitters provided on the suction knock out drum are responsible for liquid level control in the drum. Alarms are usually provided for high and high high liquid level conditions.
    14. Temperature transmitter can be provided on aftercooler for temperature control by sending a signal to adjust the fan speed of the aircooler.
    15. Emergency Shutdown (ESD) valves can be provided on inlet / outlet lines of the compressors system to isolate whole system in case of a shutdown. The inlet line of the suction KOD corresponds to inlet of the compressor system. Aftercooler discharge and liquid outlet of suction knock out drum correspond to the outlet lines of the compressor system. Shutdown valves can be located on these lines as shown in figure-1.
    16. Drains and vents to be provided on the suction / discharge lines, compressor casing, suction Knock Out Drum, air cooler body etc. for completely draining/venting compressor and associated piping, for maintenance.
    17. For purging the compressor system, a nitrogen connection can be provided right after the first isolation valve on the suction KOD inlet line.
    18. All the guidelines given here are very general and may be modified as per specific requirements of any particular project.
Don't Miss Our Updates
Be the first to get exclusive content straight to your email.
We promise not to spam you. You can unsubscribe at any time.
Invalid email address
You've successfully subscribed !

Continue Reading

P&ID Guidelines for Separator Vessels
Commissioning a Differential Pressure Transmitter in a Pressurized Boiler Steam Drum
How to Install a Rotameter
DP Level Measurement Problems
Tips for Reducing the Noise Signals
Good and Bad Wiring Practices
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Copy Link
Share
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

128.3kFollowersLike
69.1kFollowersFollow
210kSubscribersSubscribe
38kFollowersFollow

Categories

Explore More

Instrumentation Cables Armor
P&ID Guidelines for Pig Receivers
Gas Detectors Installation Techniques
How to Install Ultrasonic Level Transmitters
What is FAT and SAT? Difference between them
Installation Precautions of Thermocouple and RTD
Impulse Tubing Leak Test Checks
Flow Meter Installation Guidelines

Keep Learning

P&ID Guidelines for Storage Tanks

P&ID Guidelines for Storage Tanks

Piping and Instrumentation Diagram

What is Piping and Instrumentation Diagram (P&ID) ?

Installation and Maintenance of Control Valves

Installation and Maintenance of Control Valves

P&ID arrangement for Control Valves

P&ID Guidelines for Control Valves

Slop Tank Level Transmitter Erection

Wrong Installation of Horn Type Radar Level Transmitter on Sloping Tank

Magnetic Float Level Switch Principle

Magnetic Float Level Switch Installation Techniques

How to Solve Cable Tray Sagging

How to Solve Cable Tray Sagging ?

Triangle A-B-C- with Arc “A-C”

Instrument Tube Fitting Installation – Part 2

Learn More

Pressure Transmitter Installation

Field Instruments Mounting brackets

Difference Between Circuit Breaker and Disconnector

Difference Between Circuit Breaker and Disconnector

Starting a Synchronous Motor

Starting a Synchronous Motor

Explain operation of the circuit

Explain Operation of the Lamp Circuit ?

As-Interface Protocol Overview

AS-interface and DeviceNet Communication

Calculate Hydraulic Pressure of a Drum

Calculate Hydraulic Pressure of a Process Vessel

thermocouple head

Thermocouples Connector and Tip styles

Power Systems Questions & Answers

Power Systems MCQ Series 7

Menu

  • About
  • Privacy Policy
  • Copyright

Quick Links

  • Learn PLC
  • Helping Hand
  • Part Time Job

YouTube Subscribe

Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?