Inst ToolsInst ToolsInst Tools
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
  • Request
Search
  • Books
  • Software
  • Projects
  • Process
  • Tools
  • Basics
  • Formula
  • Power Plant
  • Root Cause Analysis
  • Electrical Basics
  • Animation
  • Standards
  • 4-20 mA Course
  • Siemens PLC Course
Reading: Factory Acceptance Test (FAT) of a PLC Panel
Share
Notification Show More
Font ResizerAa
Inst ToolsInst Tools
Font ResizerAa
  • Courses
  • Design
  • PLC
  • Interview
  • Control System
Search
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
  • Request
Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Inst Tools > Blog > PLC Tutorials > Factory Acceptance Test (FAT) of a PLC Panel

Factory Acceptance Test (FAT) of a PLC Panel

In this article, you will learn the general guidelines and how-to procedure of factory acceptance test (FAT) of a PLC Panel.

Last updated: April 18, 2023 12:24 pm
Viral Nagda
PLC Tutorials
No Comments
Share
6 Min Read
SHARE

In this article, you will learn the general guidelines and how-to procedure of factory acceptance test (FAT) of a PLC Panel.

PLC system always comes in a control panel. It is not possible to run the PLC system without a control panel.

Basically, it is the electrical panel where the PLC is mounted along with other electric devices like contactors, relays, terminal boards, fuses, circuit breakers, and bus bar. All of these components comprise an electrical panel.

Factory Acceptance Test of PLC Panel

Factory Acceptance Test of PLC Panel

Suppose you have designed a PLC system and made it ready for testing. But, you need to follow some general guidelines to see whether all the components and their wiring is proper or not. This has to be done in front of the customer before dispatching it to them. This process is called FAT (Factory Acceptance Test).

So the PLC panel will be tested at the factory and only accepted by the client if it is functioning properly as per the design documents.

Let’s study the step-by-step procedure for executing a proper FAT of the system.

You first of all created documents like the IO list, electrical drawing, GA (General Architecture) of the panel, and BOM (Bill of Materials) and sent them to the customer for approval.

So, before calling them for FAT at your factory, make sure you have two hard copies of the above-mentioned documents for verification; one for you and the other for the customer to check and approve.

Now that the client is with you and ready for inspection; first of all, let them verify all the components according to BOM (Bill of material) visually. It is to be done to ensure that all the materials that you have sold to them are present in the panel or not.

Let them verify the GA of the PLC panel and visually check whether it’s proper or not.

Let them inspect the panel outdoors, fabrication, and gland hole design approved by them. So, as you must have read, this step is the visual verification of all the documents and electrical panels before powering them up.

After the visual inspection has been done, connect the main power supply to the panel and power it up.

Check the incoming voltage with a multimeter on its terminal board. Check the voltage between earth to neutral and see if it is below 0.5V. If everything is proper, then turn on all the MCBs in the panel one by one.

Turning on the MCBs and other circuit breakers means the panel is fully charged now. So, the PLC is also powered up eventually.

Now that the PLC is powered up, you have to connect your laptop or PC to it and download the final backup in it.

After downloading, keep the PLC in run mode and see if it shows any error or not. If you have HMI or SCADA also in the panel, then download its final program too.

Now, you have to check the IOs of the PLC. According to the wiring that you have done, check digital inputs first.

On giving the input at the desired terminal point in the panel or somewhere else, the corresponding PLC input address in the program must be turned on.

Then, check the digital outputs. According to the PLC output address that you have turned on, the physical PLC output must also turn on.

When it is ON, check the output voltage across it. The output is connected to a relay board mostly. If the relay turns on, then check whether its output is given to a contactor or terminal board.

The final objective is to check the output voltage coming across the terminals. Then, check the analog inputs.

On giving the input, the corresponding PLC input address in the program must be shown analog counts accordingly.

Then, check the analog outputs. According to the PLC output address that you have given counts, the physical PLC output must also give the corresponding counts.

Check the current or voltage across the terminals where the wire is connected.

Now, sum up all the points tested and make a compliance report. Give the remarks accordingly if something is faulty or pending to be checked.

If the client gives approval after testing has been completed, then your PLC panel is ready to be dispatched and FAT has been completed.

In this way, we saw the general steps in conducting the FAT of a PLC system.

If you liked this article, then please subscribe to our YouTube Channel for Instrumentation, Electrical, PLC, and SCADA video tutorials.

You can also follow us on Facebook and Twitter to receive daily updates.

Read Next:

  • Types of Noise in Electronics
  • AS-interface Communication
  • PLC System Site Acceptance Test
  • Troubleshoot the Status of a PLC
  • Control Motion using VFD drives
Don't Miss Our Updates
Be the first to get exclusive content straight to your email.
We promise not to spam you. You can unsubscribe at any time.
Invalid email address
You've successfully subscribed !

Continue Reading

Basic Pumping System Application Used in Industrial Automation
Typical HMI Screen Design for Water Treatment Plant
How to do Scaling for Analog Input in RSLogix 500?
Sorting & Distribution Line PLC Programming – Advanced Logic
STL Programming – SET, RESET, ASSIGN
PLC Program for Control Valve Scaling
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Copy Link
Share
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

128.3kFollowersLike
69.1kFollowersFollow
210kSubscribersSubscribe
38kFollowersFollow

Categories

Explore More

PLC Instruction List Example for Level Control of Tank
Top Free PLC Software
Machine Indicator Lights: PLC Programming Solution
Pulse Timer Instruction in PLC Programming
PLC Programming for Pumping and Draining System
Label the Electrical Circuit Schematic
Basic Concepts of the Safety Relay
Traffic Light Control using PLC Ladder Logic

Keep Learning

Automatic Coffee Machine

Automatic Coffee Vending Machine – PLC Logic Programming

Siemens CPU Clock Memory

Alarm Acknowledge using PLC

Instrumentation Engineer in Process Plant Project

Instrumentation Engineer in Process Plant Project

PLC Counter Example for Bank

PLC Program for Bank Counter Application

Micro 870 Rockwell PLC

Rockwell Automation Allen Bradley PLC for Smaller and Medium Projects

PLC Fault Diagnosis - PLC Training Documents

PLC Fault Diagnosis – PLC Training Documents

Architecture of Allen Bradley PLC

Architecture of Allen Bradley PLC

PLC Stop - Start Circuit

Introduction to PLC Ladder Diagrams

Learn More

two-way communication between PLC systems

Transferring Data Across PLC Systems – TSEND_C and TRCV_C

Comparators Objective Questions

Comparators Objective Questions

What is Cloud Computing

What is Cloud Computing? Types of Cloud Services, Components

Electrical Machines Objective Questions

Electrical Machines Objective Questions

CO2 Stripper Old Differential Pressure Transmitter Stopped Working

CO2 Stripper Old Differential Pressure Transmitter Stopped Working

RAID stands for Redundant Array of Independent Disks

What is Raid Parity? – Types, Advantages, Disadvantages

Rotary Granulator Drive

Rotary Granulator Drive Root Cause Analysis (RCA)

hard disk drive

Difference Between HDD and SSD

Menu

  • About
  • Privacy Policy
  • Copyright

Quick Links

  • Learn PLC
  • Helping Hand
  • Part Time Job

YouTube Subscribe

Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?