Root Cause Analysis (RCA)

CO2 Stripper Old Differential Pressure Transmitter Stopped Working

Instrumentation engineering root cause analysis (RCA) of CO2 stripper pneumatic differential transmitter stopped working and delays the plant commissioning progress.

Article Type:Root Cause Analysis (RCA)
Category:Instrumentation
Equipment Type:Transmitters
Author:S. Raghava Chari

Note: This root cause analysis (RCA) is from real-time scenarios that happened in industries during the tenure of two or three decades ago. These articles will help you to improve your troubleshooting skills and knowledge.

Differential Pressure Transmitter Stopped Working

The CO2 stripper 5 beds Differential Pressure transmitters (DPT) stopped working within few minutes and it delays the NH3 plant commissioning progress.

CO2 Stripper Old Differential Pressure Transmitter Stopped Working

Note: This is a Pneumatic based differential pressure transmitter

Authors Root Cause Analysis

The author traced the problem to the stripper gas carried over water filling both differential pressure transmitters (DPT) leads within few minutes.

Zero suppressing for the short-height high-pressure lead is easy (as shown in the above figure).

On the other hand, no DPT offered zero elevation capability for the 20 m tall LP lead. Even the added 10 Liters LP lead bottom fitted cylinder and the entire LP lead-filled within few minutes.

The process licensor gave up the problem unsolvable.

Author Final solution

The above figure is shown 1:1 pneumatic relay (PRESSURE) was the answer: it senses the LP tap pressure and outputs equal air pressure to the LP: Port.

Zero elevation is not necessary as 1.293 Kg/Nm3 air density is negligible compared to 1000 Kg/m3. water density. Crew zero suppressed for the HP fill.  

Shop made process wetted SS-316 parts replaced the 1:1 relay process incompatible brass parts. A 0.8 mm thick PTFE disc prevents the process wetting the PRESSURE process side diaphragm; hence it lasts forever.

Realized Benefits

Realized Benefits are:

  1. Each tray reliable ▲P measurement let commission progress to completion
  2. It helps the process fine tuning
  3. A DDUDP solved at negligible costs and time

Author: S. Raghava Chari

Do you face any similar issues? Share with us through the below comments section.

If you liked this article, then please subscribe to our YouTube Channel for Instrumentation, Electrical, PLC, and SCADA video tutorials.

You can also follow us on Facebook and Twitter to receive daily updates.

Read Next:

You've successfully subscribed !
Share

Recent Articles

  • PLC Tutorials

Conveyor Sorting Machine PLC Program with Calculation Function

The conveyor sorting machine is widely used in the packing industries using the PLC program…

4 days ago
  • PLC Tutorials

Example of Flip-Flop PLC Program for Lamps Application

Learn the example of flip-flop PLC program for lamps application using the ladder logic to…

4 days ago
  • PLC Tutorials

STAR DELTA Programming using PLC Controller

In this article, you will learn the STAR DELTA programming using PLC controller to start…

5 days ago
  • Instrumentation Design

Single and Three Phase Immersion Electrical Heaters Wiring Circuits

Lube oil consoles of rotary equipment packages in industrial process plants are usually equipped with…

2 days ago
  • Instrumentation Design

Immersion Heaters in Lube Oil Consoles

Rotating equipment packages such as pumps, compressors, turbines need the lube oil consoles for their…

4 days ago
  • PLC Tutorials

How to Blink Lights in Ladder Logic?

This article explains how to blink lights in ladder logic with a detailed explanation video…

4 weeks ago