Power Plant

Ash Handling System in Thermal Power Plant

In thermal power plants, we use lot of coal for power generation. The coal has high amount of ash content, so these power plants generate lots of ash content. so we need a high efficiency system for handling the ash.

The role of ash handling system plays a crucial role to maintain the environmental norms and following industry standards.

The main interlocks in the ash handling system in thermal power plants are as follows.

  • Instrument air pressure not low
  • Conveying pressure not low
  • Silo level not high

Ash Handling System

Ash handling system consists of a control panel that contains the following parts.

  1. Seal Pressure Switch
  2. Vessel Pressure Switch
  3. Conveying Back Pressure Switch
  4. Dome Cylinder Solenoid Valve
  5. Conveying Air Solenoid Valve
  6. Level Switches
  7. Push-button, Indication lamp, Selector switch
Ash Handling System in Thermal Power Plant

Seal Pressure Switch

This is used to continuously monitor the seal pressure if it goes beyond the set point indication and its signal connected to the PLC.

If this signal appears on the PLC, then the operator checks the system where the seal may get damaged or cylinder link issue, pneumatic hose damage, or any other problems in the system.

Vessel Pressure Switch

 If the vessel line has any blockade then the vessel pressure switch will be activated. Then continue purging goes ON still the blockage not cleared.

In this case, the operator has to open the line and clear the block.

Conveying Back Pressure Switch

Conveying back pressure switch is used to OFF the system when continue conveying goes ON for some time.

Dome Cylinder Solenoid Valve

 The solenoid valve is used for the open and close operation of the dome cylinder. So that ash goes to silo

Conveying Air Solenoid Valve

After deposit, the ash in the vessel conveying air moves the ash to the silo when conveying air solenoid open.

Level switches

RF Admittance type and ultrasonic type level switch can be used for ash level identification.

The high-level switch is used for instrument interlock used for probe mode and timer mode.

High-high level switch also used for electrical trip.

Push-button, Indication lamp, Selector switch

Local start stop available.

Conveying air push button.

Indicator lamp is used to provide a simple LED display i.e. on or off status.

Modes of Operation

Ash handling system can run in two modes

  1. Timer mode
  2. Probe mode

Timer mode Principle

In PLC or DCS, the time setting of each ash handling system depends on ash collection.

Initially, the system starts, the purging will go automatically for clearing the lines initially. If the line has a choke vessel pressure high indication then it will come in PLC or DCS then purging will goes on continuously to clear the choke.

Then the seal open command comes to the solenoid valve after that dome seal opens using a pneumatic cylinder.

Ash will be deposit in the vessel for a particular time. After the dome seal closed conveying air solenoid gets energized. The coveying air will flow and takes the ash to the silo where ash deposits.

Again, the timing of the ash handling system will change when the high-level switch activated.

Probe Mode Principle

In this mode, the system will run continuously when the high-level switch activated. The system running will be stopped after the level normalized.

Author: Sivachidambaram

You've successfully subscribed !

View Comments

Share

Recent Articles

  • PLC Tutorials

PLC Ladder Logic Design: Control 3 Motors with Toggle Switch

PLC ladder logic design to control 3 motors with toggle switch and explain the program…

3 weeks ago
  • PLC Tutorials

VFD Simulator Download – Free Yaskawa V1000 Software

VFD simulator download: Master the online tool from the Yaskawa V1000 & programming software for…

3 days ago
  • PLC Tutorials

Conveyor Sorting Machine PLC Program with Calculation Function

The conveyor sorting machine is widely used in the packing industries using the PLC program…

6 days ago
  • PLC Tutorials

Example of Flip-Flop PLC Program for Lamps Application

Learn the example of flip-flop PLC program for lamps application using the ladder logic to…

6 days ago
  • PLC Tutorials

STAR DELTA Programming using PLC Controller

In this article, you will learn the STAR DELTA programming using PLC controller to start…

7 days ago
  • Instrumentation Design

Single and Three Phase Immersion Electrical Heaters Wiring Circuits

Lube oil consoles of rotary equipment packages in industrial process plants are usually equipped with…

4 days ago