Control Systems

PLC or DCS Control System Spares

In general, spares in the control system (PLC or DCS) are defined as consumable spares, commissioning spares, installed spares, 2 years operational spares, and mandatory spares.

Control System Spares

Consumable spares and commissioning spares

Consumable spares and commissioning spares are normally recommended by the system vendor supplier.

These spares are meant to be consumed before the system is fully operational and these are required to avoid using any of the recommended operational spares. These spares are ordered along with main items.

For instance, Fuses, terminals, relays, printer cartridges, A3/A4 papers, and so on.

Installed spares

Installed spares as the name indicate, are installed within the control system. These spares are utilized when there is the failure of a component within the system so by using installed spare; the system is operational without any downtime.

The requirement of installed spare shall be defined as part of the project scope. Assume if one channel from 16 channel I/O card is not working then it is reconfigured with an installed spare within that I/O module.

Wired spares (as part of installed spare) are a ready-to-operate condition when field cable is connected to spare assigned terminals. Installed spares serve the purpose of replacement and/or future expansion/modification of the system.

Therefore, it has a significant role in overall control system design and its capacity.

2 Years Operational Spares

2 Years operational spares are essential for the continual operation of the control system. This set of spare includes small items (fuses, relays) to large items (Controllers, servers). The scope of supply of these spares depends upon the project scope.

However, a list of recommendations can be provided by the control system vendor. These spare parts are in form of loose supply and not installed into the system.

On contrary, few spares take longer delivery time, hence, it is beneficial to have them in the warehouse to ensure the continual operation of the plant.

Mandatory Spares

Once in a while, the mandatory spares are described as a part of the project scope. These are also loose spares like 2 Years operational spares and can be used in a lieu of 2 years operational spares.

These spares are used for the substitution of failed components or can also be used for future expansion.

Predominantly, spare space is also considered within the control system to ensure future capacity expansion.

Spare Requirement

It is paramount to understand the spare requirement defined in projects.

  • 20% installed, wired, and fully functional I/O for all types(including Field Termination Arrays or equivalent)
  • Spares in I/O modules are not necessarily identical as spares required in mutlipair/ or multi core cable.
  • Spare pairs of the incoming cables should be terminated on spare terminals in the marshalling cabinets.
  • Since I/O Module is specified as wired, it means that wiring up to I/O module is also needed along with associated accessories.
  • These spares are required for each type of I/O channels; these shall be fully wired from the terminal block, relay, fuses, barriers, etc. This is a paradigm of installed spare.
  • For instance, if you have analog input as 2 wire, 3 wire, 4 wire, analog interface with MCC, IS type, Non IS type then you should have all these I/O as spare for each type. Analog input channels with different I/O adaptor should also be considered as different I/O type.
  • Also, this spare should be dedicated to each type of system (e.g. DCS, ESD, and F&G). Each system should have evenly distributed spare I/Os. It is worthless to provide 30% Spares in DCS and 10% spares in ESD and 20% in the F&G system.
  • These spares are required as cumulative, not as per individual location/cabinet wise. Suppose your control system is spread over various locations within the plant (Remote I/O panels), then in each location, you may not need to meet 20%. However, as a total, you should meet the requirement.
  • Since installed spare I/Os are wired up to I/O modules, processor loading should be inclusive of installed spares then processor spare capacity should be calculated. This is grey area for many. Hence, this shall be mutually agreed upon.
  • Spare Space in the cabinet: Minimum 20% free space.
  • 20% spare capacity in trunk/duct after cabling and wiring has been installed
  • Even if the installed spares are installed within the cabinet, 20% free space is also necessitated to install components like I/O modules, Terminals, barriers, or even controllers for future capacity expansion. Hence, the associated cable duct should also have some spare space for wiring.

Spares Calculation

Additional examples of installed spares are as follows

  • Cable gland plate: 20% spare space in cable gland plate of the cabinet
  • Fibre Optic: 100% spare fibers in fiber optic cable
  • Power supply: 25% spare capacity after completion of SAT
  • System memory (RAM): 50% spare capacity in each workstation/server
  • Storage capacity: 50% spare capacity in each workstation/server after completion of SAT
  • Software license: 50% spare capacity in each workstation/server
  • Controller /processor loading: 40% spare capacity after completion of SAT
  • Network loading: 40% spare capacity after completion of SAT

Understanding of Spare Parts and Spare Space

Sometimes, it is pivotal to have a clear mutual understanding of spare parts and spare space when there are ambiguous requirements specified.

  • Location-wise or cabinet wise spare I/Os or terminals requirement.
  • When you have universal or configurable I/O types then spare I/O types requirement can be optimized and overall spare requirement can be mutually agreed upon as part of the contract.
  • Spare space should be altogether considered in each type of cabinet. It has no meaning to provide one spare cabinet and fully load the other cabinets.
  • It is essential to consider spare accessories like a relay, barriers/isolators, adaptors, fuse along with each type of I/Os especially when spare accessories are not specified in the project specification.

It is more appropriate to ask in case of unclear requirements as it will have an impact on overall control system design and related deliverables such as

  • I/O assignment,
  • Cabinet GA Diagram,
  • Bill of Materials, etc.

Author: Jatin Katrodiya

If you liked this article, then please subscribe to our YouTube Channel for PLC and SCADA video tutorials.

You can also follow us on Facebook and Twitter to receive daily updates.

Read Next:

You've successfully subscribed !

View Comments

  • For PLC or DCS System 2 Years Spare Part, is that mandatory to make a spare part stocks beside DI/DO/AI/AO module, like Communication Module, Bus Adapter, Interface Module, or even CPU Module?

    Thanks for your answer

Share

Recent Articles

  • PLC Tutorials

Example PLC Program to Control a Pump based on Level Sensors

Learn an example PLC program to control a pump based on level sensors using ladder…

2 weeks ago
  • PLC Tutorials

PLC Timer Application in Security Camera Recording

In the PLC timer application for security camera recording, when motion is detected then camera…

2 weeks ago
  • PLC Tutorials

Batch Mixing with PLC Ladder Logic Program

In this example, we will learn batch mixing with PLC ladder logic program using timer…

2 weeks ago
  • PLC Tutorials

PLC Example on Manufacturing Line Assembly

This PLC example on manufacturing line assembly is an intermediate-level PLC program prepared for the…

2 weeks ago
  • PLC Tutorials

PLC Programming Example with Pushbutton and Motor

In this article, you will learn the PLC programming example with pushbutton and motor control…

3 weeks ago
  • PLC Tutorials

Boolean Logic to PLC Programming

This article teaches how to convert Boolean logic to PLC programming ladder logic with the…

1 month ago