Inst ToolsInst ToolsInst Tools
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
  • Request
Search
  • Books
  • Software
  • Projects
  • Process
  • Tools
  • Basics
  • Formula
  • Power Plant
  • Root Cause Analysis
  • Electrical Basics
  • Animation
  • Standards
  • 4-20 mA Course
  • Siemens PLC Course
Reading: What are Pre-Shutdown, Shutdown, and Post-Shutdown?
Share
Notification Show More
Font ResizerAa
Inst ToolsInst Tools
Font ResizerAa
  • Courses
  • Design
  • PLC
  • Interview
  • Control System
Search
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
  • Request
Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Inst Tools > Blog > Basics > What are Pre-Shutdown, Shutdown, and Post-Shutdown?

What are Pre-Shutdown, Shutdown, and Post-Shutdown?

Last updated: September 28, 2022 2:40 pm
R Jagan Mohan Rao
Basics
1 Comment
Share
4 Min Read
SHARE

Basically a plant maintenance shutdown is split into three steps, which are as follows:

Contents
Pre-shutdown:Shutdown Initiation PhaseShutdown PlanningShutdown:Post-shutdown:
  1. Pre shutdown
  2. Shutdown
  3. Post shutdown

Pre-shutdown:

Pre-shutdown is preparation for the shutdown. It is classified into three distinctive phases

  1. Shutdown initiation
  2. Shutdown planning
  3. Scheduling

Shutdown objectives are

  1. Zero harm to the workforce
  2. Shutdown costs to be withing budget cost.

Shutdown Initiation Phase

In the shutdown initiation phase, objectives are clearly defined. Such as

  • Shutdown date
  • Shutdown duration
  • Shutdown budget
  • Shutdown objectives
  • List of equipment to be taken offline
  • Scope of work for equipment taken offline
  • Equipment to be modified
  • Who will manage, execute shutdown?
  • Key dates for shutdown phase

Shutdown Planning

The planning phase starts one year, two years ahead of a shutdown is carried out depending upon the organization to organization. It is about a shutdown workforce, identifying parts, labor, equipment, and other resources. By the involvement of high-level meetings with the involvement of operation, maintenance, and engineering departments.

Shutdown Manager

In the planning phase, long interval time is to be identified, as necessary items are procured and stored.

Labor: the size of the extra labor requirements must be identified and organized. Service orders for contractors to be initiated, specialists resources must be identified and planned for his or her mobilization.

Equipment: requirement for specialized things like handtools, cleaning equipment, heavy lifting equipment, forklifts.

Scheduling: A passionate shutdown team is appointed. Shutdown schedulers, shutdown planners are given separate responsibilities.

Identifying shutdown priorities and then shutdown schedules according to priorities.

Planning determines what, how and why the work is being administered.

Scheduling determines who and when the work is to be administered.

Scheduling requires a great deal of coordination and organizing to bring the upkeep program together.

Shutdown:

When it comes to the shutdown, execution is with only one step. Shutdown normally planned for 30-45 on average.

Initially, when the zero date starts, all the operations are closed, equipment is internally cleaned and manholes are opened. Preliminary equipment internals and externals are inspected, some additions are made after internal-external inspections.

Following are the steps preparing equipment to be shutdown require the equipment to be

Plant Shutdown Activities

Plant maintenance supervisory staff are responsible for driving shutdown execution. They use work packs by the shutdown planner in conjunction with the shutdown scheduler to complete the task within a stipulated time.

Shutdown supervisors/Engineers must update work progress regularly to shutdown scheduler even shift wise. The shutdown scheduler is then responsible for monitoring the overall progress of the shutdown. Review meetings chaired by shutdown manager are carried out to smooth functioning of the shutdown process.

Instrumentation activities such as isolation of field instruments, servicing, calibration fixing back and loop checking is to be carried out as per scheduler.

The engineering inspection team evaluates the quality of work. Everything is checked and reverified the box up activity starts.

Engineering Inspection Team

Post-shutdown:

Once the shutdown completion is notified, all the supporting equipment go offsite.

Post shutdown analysis is carried out soon after the shutdown is completed.

The shutdown maintenance process must be well documented and can be utilized for planning future shutdowns.

The secret fo a successful shutdown is the result of preparation, hard work and learning from failure.

Read Next:

  • Emergency Shutdown Philosophy
  • Compressor Shutdown RCA
  • Shutdown Valve
  • Instrument Maintenance
  • Maintenance Override Switch
Don't Miss Our Updates
Be the first to get exclusive content straight to your email.
We promise not to spam you. You can unsubscribe at any time.
Invalid email address
You've successfully subscribed !

Continue Reading

Resistor Color Code Animation
Why 4-20 mA Current Signal is used instead of Voltage Signal?
What is Instrumentation and Control ?
Sink or Source? Normally Open or Normally Closed?
Instrumentation Abbreviations
How to Convert Current to Voltage using Resistor ?
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Copy Link
Share
1 Comment
  • tedros says:
    March 17, 2024 at 4:49 pm

    good explanation

    Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

128.3kFollowersLike
69.1kFollowersFollow
210kSubscribersSubscribe
38kFollowersFollow

Categories

Explore More

Basics of Loop Checks
Basics of Trips, Interlocks, Permissives & Sequences
What Every Instrument Engineer Should Know?
Impulse Piping standards for Field instruments
Difference between Accuracy, Tolerance, Uncertainty, and Error
What is a Ground Rod?
What is Power Cable? Types of Power Cables
Control and Instrumentation Engineer Study Guide

Keep Learning

Sensors and Transducers Classification

Sensors and Transducers Classification

Electrical Conduit

What is Electrical Conduit? Types, Advantages, Disadvantages

Why 4-20 mA Current Signal is used instead of Voltage Signal

Troubleshooting a 4-20mA Current loop

Instrumentation Logic Checks

How to Do Logic Checks During Plant Pre-Commissioning

HART Transmitters Loop Checks

Loop Check of 4-20mA or HART Transmitters

4-20mA Current Loop Components

Why Use a Current Loop?

Smart Sensors in Industry

Smart Sensors in Industry – Components, Types, Advantages

Instrumentation Dictionary

Instrumentation Dictionary

Learn More

Analog Electronics Objective Questions

Analog Electronics Objective Questions – Set 9

Applications of Photo diodes

Applications of Photo diodes

Analyzers Questions and Answers

Ionization of Gases Questions and Answers

Industrial Automation Cold and Hot Standby

Difference between Cold Standby and Hot Standby

Compounded DC Generator

Compound Generators

PLC Motor Control Circuit-3

Basics of PLC Programming

Chromatography Questions & Answers

Detection System of Liquid Chromatography Questions & Answers

transistor-emitter-bias

Transistor Emitter Bias

Menu

  • About
  • Privacy Policy
  • Copyright

Quick Links

  • Learn PLC
  • Helping Hand
  • Part Time Job

YouTube Subscribe

Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?