Inst ToolsInst ToolsInst Tools
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
Search
  • Books
  • Software
  • Projects
  • Process
  • Tools
  • Basics
  • Formula
  • Power Plant
  • Root Cause Analysis
  • Electrical Basics
  • Animation
  • Standards
  • 4-20 mA Course
  • Siemens PLC Course
Reading: Workstation Healthiness Checks
Share
Notification Show More
Font ResizerAa
Inst ToolsInst Tools
Font ResizerAa
  • Courses
  • Design
  • PLC
  • Interview
  • Control System
Search
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Inst Tools > Blog > PLC Tutorials > Workstation Healthiness Checks

Workstation Healthiness Checks

Last updated: March 4, 2021 12:31 pm
Editorial Staff
PLC Tutorials Control Systems
1 Comment
Share
2 Min Read
SHARE

The below-mentioned healthiness checks are carried out for the control room workstation which will help you to improve the life span of the DCS and PLC HMI systems.

Workstation Healthiness Checks

Workstation Healthiness Checks

Steps to be followed to check the healthiness of WORKSTATION:

1. Collect the corresponding Work permit.

2. Note down the HIS (Human Interface Station, also called workstation) tag name which will be available on both sides of the console. or as follow your system details.

3. Login into administrator user on a particular workstation.

4. Note down the drive memory details of that particular system by clicking My Computer icon.

5. Note down the antivirus status by placing the cursor on the antivirus icon in the taskbar. If you have the latest version then update the antivirus software using the CD.

6. Right-click on the taskbar select start task manager, click on performance, note down the CPU and RAM usage. It must be within the limits. ( As per the limits defined in your plant system philosophy).

7. Check the console cooling fans running status.

8. Measure the utility supply voltage from MCB which will be on the backside of the console.

9. Check the workstation, mouse, keyboard, monitor condition (clean the system from the dust).

10. Clean up any unwanted data files.

11. Check the network status ( Lights will blink at Ethernet ports backside of CPU)

12. Logoff the administrator user then log in to the operator user.

13. Check the sealing of spare cable entry slots at bottom of the panel.

14. Check for any loose connections in the panel.

15. Clean all the filters of the panel using a vacuum cleaner (outside).

16. Check and ensure cables are properly dressed and cable ducts are covered.

If you liked this article, then please subscribe to our YouTube Channel for PLC and SCADA video tutorials.

You can also follow us on Facebook and Twitter to receive daily updates.

Don't Miss Our Updates
Be the first to get exclusive content straight to your email.
We promise not to spam you. You can unsubscribe at any time.
Invalid email address
You've successfully subscribed !

Continue Reading

What is Ladder Diagram Programming ?
PLC Connection between Instrument, Junction Box, Marshalling & System Cabinet
Tia Portal – OB30 Cyclic Interrupt Organization Block
Siemens PLC Interview Questions and Answers
PLC Programming Example on Bottle Line Control
How-to Create Instrument Loop Diagram (ILD)?
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Copy Link
Share
1 Comment
  • R.JAGAN MOHAN RAO says:
    May 3, 2020 at 1:26 pm

    Very good information on the health check procedure.

    Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

128.3kFollowersLike
69.1kFollowersFollow
208kSubscribersSubscribe
38kFollowersFollow

Categories

Explore More

D Flip Flop PLC Ladder Logic
ICS System Design Considerations
Top Free PLC Software
Waste Water Control System
Types of Surge Control for Parallel Gas Compressors
Difference between Availability, Reliability & SIL
Series Tanks Level Control using PLC Ladder Programming
PLC Example on Manufacturing Line Assembly

Keep Learning

Batch mixing process automation with Omron PLC

Automate Batch Mixing with Repeated Cycles in Omron PLC

Communication between Intouch Scada and Allen Bradley PLC

Communication between InTouch Scada and Allen Bradley PLC

SCADA System

What is SCADA System?

Digital Output Card With Relay and Wet Contact

Wiring Diagrams of PLC and DCS Systems – DI, DO, AI, AO

Single Line Diagram of UPS System

UPS Selection Factors for a Control System

PLC Wiring

PLC Wiring Questions for Technicians and Engineers

Opposite Acting Control Valves Application

PLC Ladder Logic for Opposite Acting Control Valves Application

How to Upload PLC Program in Siemens PLC if Upload Icon is Disabled

Upload Option Disabled in Siemens PLC

Learn More

Liquid Nitrogen in Instrumentation

Liquid Nitrogen in Instrumentation

A Question on Density Gauge

stepper motors Animation

Fundamentals of DC Motor Animation

Potential Difference Across a Conductor Causes a Current to Flow

Conductor, Insulator, Resistor and Current Flow

Ethernet Switch Animation

Ethernet Bus Animation

Closed Tank Level Measurement using DP Transmitter

How can we use a DP Flow Transmitter for Level Measurement

PLC Motor Logic with START, STOP, TEST Push buttons

PLC Motor Logic with START, STOP, TEST Push buttons

Power Electronics Objective Questions

Current Source Inverters Objective Questions

Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?