Siemens S7-200 PLC Questions and Answers
Suppose we have a Siemens S7-200 PLC connected to a pair of process switches and light bulbs as shown in this illustration:
Examine the following relay ladder logic (RLL) program for this Siemens PLC, determining the statuses of the two lamps provided the temperature switch senses 102 oF and the flow switch senses 4.7 GPM:
Also, determine whether the inputs on this PLC are sourcing or sinking, based on how they are connected to the process switches.
Green lamp is off, red lamp is on. The PLC inputs are configured here to sink current.
Share Your Answer / Comments
Credits : Tony R. Kuphaldt – under CC BY 1.0
PLC ladder logic design to control 3 motors with toggle switch and explain the program…
VFD simulator download: Master the online tool from the Yaskawa V1000 & programming software for…
The conveyor sorting machine is widely used in the packing industries using the PLC program…
Learn the example of flip-flop PLC program for lamps application using the ladder logic to…
In this article, you will learn the STAR DELTA programming using PLC controller to start…
Lube oil consoles of rotary equipment packages in industrial process plants are usually equipped with…