Find the latest EPC Questions and Answers for engineers working in Engineering, Procurement, Construction related industries.
RevA – Process Input with client comments, RevB – Mechanical Input Required, RevC – Submit with Inquiry for Client Approval, RevD – Submit to vendors for quotation, Rev0 – Submit with purchase requisition after bid tab process.
You must validate the document. This process is so that you check the document to ensure it was tagged properly and to verify that it was received on the Vendor information requirement form.
Series – To discourage similar comments made by various parties. It is engineering consultants’ responsibility to own the design on vendor data, so we must do our diligence in commenting on vendor data per specs.
Engineering Consultants’ Stamp – It signifies that the document has been reviewed and proper approvals provided.
No, the client approves them in SAP when they release the order to the winning vendor.
So that the datasheet lives in the server as its own entity as it is issued.
Yes, provided that the comments on the original receipt documents can be easily verified by you. If you don’t understand the comments, then you should send it back to experts.
Appointed Engineering Consultants’s Engineer & Client’s Appointed engineer responsible for the project – Specialty Engineering gets involved for high alloys
E+A: Electronic plus approval, E+C: Electronic plus comment, E electronic. Must hold for E+A.
You should make every attempt to call, email, contact the client to encourage comments or timely approval, if the schedule is going to slip and all attempts have yielded no results, you are allowed to send Engineering Consultants’ comments back to the vendor without proper client input.
No, provided that there is no scope or design change, the client is expected to make all their comments and input known on the first receipt of vendor data. From 2nd round onward, Engineering Consultant is expected to turn around documents within 1 week’s time, unless otherwise directed by the schedule.
Author: Rahul Kapoor
In this article, we are going to discuss about shutter door control using induction motor…
Electrical Drives control the motion of electric motors. Motion control is required in industrial and…
PLC ladder logic design to control 3 motors with toggle switch and explain the program…
VFD simulator download: Master the online tool from the Yaskawa V1000 & programming software for…
The conveyor sorting machine is widely used in the packing industries using the PLC program…
Learn the example of flip-flop PLC program for lamps application using the ladder logic to…