Root Cause Analysis (RCA)

Condensate Pump Frequent Wrecks Threatens Long Plant Outages

Root Cause Analysis (RCA) related to the Condensate Pump Frequent Wrecks Threatens Long Plant Outages.

Article Type:Root Cause Analysis (RCA)
Category:Mechanical
Equipment Type:Miscellaneous Rotating Machine Problems
Author:S. Raghava Chari

Note: This root cause analysis (RCA) is from real-time scenarios that happened in industries during the tenure of two or three decades ago. These articles will help you to improve your troubleshooting skills and knowledge.

Problem

Several large steam turbines condensers condensate collects into two buried tanks. The tanks to 20% is above ground (below figure).

Tank 1 has top mounted turbine driven submerged pump and tank 2 motor driven same standby pump.

During many pump changeovers many pumps’ carbon bushes supporting the long shaft coupling to the drive failed. At nearly all spares used up condition the belabored engineer sought the author’s SOS help.

Surface Condenser Condensate Evacuation Pumps

Author Solution

The root cause analyzing witnessed a pump changeover: Operators opened the 3” waterside valve (above figure) to fill the condensate collection tank. They were about to push the motor start PB.

 Hold, shouted the author and asked, “Have you opened the steam side valve?” The perplexed operator grinned and said, “Steam side valve, Sir, no supervisor told me to open it”.

The author called the operations engineer and he too was ignorant of the steam side valve. The author explained, “the condenser is under high vacuum. Hence, unless the pit tank top is open to the same vacuum water cannot flow into the tank.

Hence, you must open both the ¾” steam side and the 3” water valves and wait for 5 minutes to be sure of enough condensate collection to submerge the pump. So far you have been wrecking pumps because of dry running!”              

The sheepish operator opened the steam side valve also, waited 5-minutes and then changed over to the motor driven pump safely. Thus, the author prevented another wreck and all future wrecks!

By a memo, the author requested the operations manager to revise the pump start up procedure and to hold classes for all operators, and shift engineers in Arabic.

Author: S. Raghava Chari

Do you face any similar issues? Share with us through the below comments section.

If you liked this article, then please subscribe to our YouTube Channel for Instrumentation, Electrical, PLC, and SCADA video tutorials.

You can also follow us on Facebook and Twitter to receive daily updates.

Read Next:

You've successfully subscribed !
Share

Recent Articles

  • PLC Tutorials

PLC Panel and MCC Panel Interface Signals

The PLC panel and MCC panel interface signals are start, stop, run feedback, trip, local…

4 days ago
  • PLC Tutorials

Shutter Door Control using Motor and Limit Switches

 In this article, we are going to discuss about shutter door control using induction motor…

6 days ago
  • Electrical Basics

Electrical Drives – Modes, Types, Speed Control Applications

Electrical Drives control the motion of electric motors. Motion control is required in industrial and…

6 days ago
  • PLC Tutorials

PLC Ladder Logic Design: Control 3 Motors with Toggle Switch

PLC ladder logic design to control 3 motors with toggle switch and explain the program…

3 weeks ago
  • PLC Tutorials

VFD Simulator Download – Free Yaskawa V1000 Software

VFD simulator download: Master the online tool from the Yaskawa V1000 & programming software for…

6 days ago
  • PLC Tutorials

Conveyor Sorting Machine PLC Program with Calculation Function

The conveyor sorting machine is widely used in the packing industries using the PLC program…

9 hours ago