Inst ToolsInst ToolsInst Tools
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
Search
  • Books
  • Software
  • Projects
  • Process
  • Tools
  • Basics
  • Formula
  • Power Plant
  • Root Cause Analysis
  • Electrical Basics
  • Animation
  • Standards
  • 4-20 mA Course
  • Siemens PLC Course
Reading: Pre-Startup Safety Review (PSSR)
Share
Notification Show More
Font ResizerAa
Inst ToolsInst Tools
Font ResizerAa
  • Courses
  • Design
  • PLC
  • Interview
  • Control System
Search
  • Courses
  • Automation
    • PLC
    • Control System
    • Safety System
    • Communication
    • Fire & Gas System
  • Instrumentation
    • Design
    • Pressure
    • Temperature
    • Flow
    • Level
    • Vibration
    • Analyzer
    • Control Valve
    • Switch
    • Calibration
    • Erection & Commissioning
  • Interview
    • Instrumentation
    • Electrical
    • Electronics
    • Practical
  • Q&A
    • Instrumentation
    • Control System
    • Electrical
    • Electronics
    • Analog Electronics
    • Digital Electronics
    • Power Electronics
    • Microprocessor
Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Inst Tools > Blog > Standards > Pre-Startup Safety Review (PSSR)

Pre-Startup Safety Review (PSSR)

Last updated: March 26, 2019 11:29 am
Editorial Staff
Standards
1 Comment
Share
7 Min Read
SHARE

The term Prestartup Safety Review (PSSR) first received prominence in the process industries with the introduction of the Process Safety Management (PSM) regulations.

Contents
What is the Pre Startup Safety Review or PSSR?What is purpose of the Pre Startup Safety Review?The main activities in a PSSR of a projectPre Startup Safety Review (PSSR) Practices

In the United States two federal agencies, the Occupational Safety & Health Administration (OSHA) and the Environmental Protection Agency (EPA) require that companies conduct prestartup safety reviews.

The wording of the two standards regarding PSSRs is virtually identical, although the industries covered and the reporting requirements differ slightly.

The fundamental purpose of a prestartup safety review is to ensure that any changes that are made to a facility or item of equipment meet the original design or operating intent.

The PSSR aims to catch any changes that may have crept into to the system during the detailed engineering and construction phases of a project. PSSR covers not only equipment, but also ‘soft’ issues, such as operating procedures and training.

PSSRs play a particularly important role in large projects because such projects all too often fall behind schedule and/or run over budget, thus creating pressure on the project team to eliminate or postpone the installation of any items that are not absolutely necessary for the start-up. If not controlled properly, this can lead to corner-cutting ⎯ either intentional or inadvertent ⎯ which may then jeopardize safety.

By carrying out a PSSR, the operations and maintenance departments have the authority to refuse to accept responsibility for a plant or item of equipment that they judge to be unsafe. In effect, a prestartup safety review provides a breathing space for everyone to make sure that the plant that they are about to start is safe and operable.

It is not the purpose of a PSSR to replace this normal ‘punching out’ of a new or modified facility. Indeed, one of the purposes of a PSSR is to make sure that routine checking processes were in place and that they were followed. Nor is a PSSR a last-minute hazards analysis.

The PSSR team will typically check that a hazards analysis was carried out on the proposed changes, and that all the findings were implemented or closed out in a professional manner, but the PSSR does not aim to identify new hazards.

What is the Pre Startup Safety Review or PSSR?

The PSSR is a safety review conducted prior to startup (commissioning) of a new or modified processing/manufacturing plant or facility to ensure that installations meet the original design or operating intent, to catch and re-assess any potential hazard due to changes during the detailed engineering and construction phase of a project. In other words, it ensures the “Ready for Start-up” status of process facility/units.

A Pre Startup Safety Review covers not only equipment, but also procedures and training.

Pre Startup Safety Review procedure/guideline is normally prepared as part of Pre-commissioning/ commissioning documentation.

What is purpose of the Pre Startup Safety Review?

  • To ensure that installation meets the original design and operating intent of process plant/facility
  • To ensure safety, operating, maintenance and emergency procedures are in place and adequate
  • To ensure appropriate safety reviews during engineering phase (HAZOP study, model review etc.) have been carried out and all action items have been completed
  • To ensure any site modifications during construction phase have been properly controlled and noted
  • To ensure training of each employee involved in the operating process is completed
  • In addition, the pre startup safety review plays an important role in large projects as it may give plant operators the authority to refuse or accept responsibility for a plant or equipment that they judge to be unsafe through the PSSR.

The main activities in a PSSR of a project

Following activities are carried out in a PSSR with coordination between Contractor and Owner of the plant / facilities:

  • Coordinate PSSR participation from knowledgeable Contractor and Owner personnel
  • Conduct Technical and HSE reviews of documentation and on site
  • Verify all construction and equipment is in accordance with safety, environmental and health regulation and standards.
  • Complete all corrective action items raised in the PSSR
  • Complete Post- Start-up corrective action items
  • Representative of the Project Owner sign the PSSR checklists for approval of commissioning/start-up of the plant
  • Documentation of PSSR

Pre Startup Safety Review (PSSR) Practices

PSSR is conducted by a team, lead by a Leader. The leader is normally a representative of operation group because they are the ultimate customer of the facility. A PSSR normally consists of 3 steps:

1. Follow-up HAZOP Review: includes the following activities:
  • Investigation on the follow-up action items provided by project on recommendations from previous HAZOP study
  • Systematic review of all changes to the design since the previous HAZOP study

The support documents for follow-up HAZOP review should be:

  • Engineering Flow Schemes or PFDs
  • Utility Flow Schemes or UFDs
  • Lists of site modifications since the original HAZOP study
  • Process Safeguarding memorandum
  • Operating and control philosophy, Cause and effect diagram
  • Other support documentation
2. Documentation Review:

The documentation review is to check the availability and status of operating manuals, start-up/shutdown and emergency procedures. Following documents should be checked for availability and status:

  • Operating manuals/procedures
  • Emergency procedures
  • Instruction of handling of chemicals
  • Operation checklists on safety equipment
  • Safeguarding Memorandum
  • As-built P&IDs/PFDs
  • Area Classification drawings, Plot Plans
  • Fire Protection drawings
3. Technical HSE Site Review:

It could be carried out when the construction is nearing mechanical completion (about 90-95 % completion) and the site is reasonably accessible. The site review will concentrate on such issues as:

  • Equipment operability and maintainability
  • Outstanding punch list items from mechanical completion associated with PSSR
  • Access and exit routes for operators and maintenance personnel
  • Small-bore connections
  • Location of emergency and safety equipment, warning signs
  • Safe location of vent lines
  • Locking systems
The PSSR checklists shall be completed by each discipline. A sample of operation checklist is given in following table:

Pre-Startup Safety Review-1

Pre-Startup Safety Review-2

Don't Miss Our Updates
Be the first to get exclusive content straight to your email.
We promise not to spam you. You can unsubscribe at any time.
Invalid email address
You've successfully subscribed !

Continue Reading

Transmitters 4-20mA Current Failure Alarm Limits
Flammable Facts
Difference between Intrinsically Safe and Flameproof Equipment ?
Instrumentation Cables Testing Standards
NFPA Standards (National Fire Protection Association Standards)
What is HAZOP ?
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Copy Link
Share
1 Comment
  • TS says:
    June 29, 2020 at 10:33 am

    GOOD

    Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

128.3kFollowersLike
69.1kFollowersFollow
210kSubscribersSubscribe
38kFollowersFollow

Categories

Explore More

Pressure Standards
Intrinsic Safety Protection ia and ib
Standard Temperature and Pressure Conditions
Why is IEC 60269 Important? – Electrical Applications
Difference Between IEC 60909 and IEC 61363 for Short Circuit
Explosive Atmospheres & Hazardous Classification
Zone vs Class / Division
List of Valve Standards

Keep Learning

Instrumentation Standards

Instrumentation Standards Questions & Answers

Instrumentation Standards Questions and Answers

Hazardous Area Classification Comparison

Comparison of IEC & NEC Area Classifications

Difference between Explosion Proof and Intrinsically Safe

Difference between Explosion Proof and Intrinsically Safe

Ingress Protection Standard

Ingress Protection Rating

Flammable Gases and Vapors Class 1 & Class 2

Gas Detectors Standards

Hazardous Area Terminology

Hazardous Area Terminology

Interview Questions & Answers on Alternators

Instrumentation Engineering Standards Questions & Answers

Learn More

Gas Detection Definitions

Standard Gas Detection Definitions

Bubbler Liquid Level Transmitter Calculation

Bubbler Liquid Level Transmitter Calculation

Pinch Valve

What is Pinch Valve ?

Pitot tube

Pitot Tube Flowmeter Calculations

Field Transmitter Damping

What is Field Transmitter Damping ?

Absorption Chiller Principle - HVAC System

HVAC Double Effect Absorption Chiller

Single Phase Half-controlled Rectifier RL Load With FD

Phase-Controlled Half-Wave Rectifier With Freewheeling Diode

Power Electronics Objective Questions

Full Wave Diode Rectifier Quiz

Menu

  • About
  • Privacy Policy
  • Copyright

Quick Links

  • Learn PLC
  • Helping Hand
  • Part Time Job

YouTube Subscribe

Follow US
All rights reserved. Reproduction in whole or in part without written permission is prohibited.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?